{"id":1213,"date":"2026-06-10T05:29:55","date_gmt":"2026-06-10T05:29:55","guid":{"rendered":"https:\/\/www.srinsoft.engineering\/blogs\/?p=1213"},"modified":"2026-06-11T04:52:11","modified_gmt":"2026-06-11T04:52:11","slug":"common-equipment-layout-mistakes-that-slow-down-piping-and-plant-industrial-projects","status":"publish","type":"post","link":"https:\/\/www.srinsoft.engineering\/blogs\/common-equipment-layout-mistakes-that-slow-down-piping-and-plant-industrial-projects\/","title":{"rendered":"Common Equipment Layout Mistakes That Slow Down\u00a0Piping and Plant\u00a0Industrial Projects\u00a0"},"content":{"rendered":"\n<figure class=\"wp-block-image size-large\"><img loading=\"lazy\" decoding=\"async\" width=\"1024\" height=\"538\" src=\"https:\/\/www.srinsoft.engineering\/blogs\/wp-content\/uploads\/2026\/06\/SSE-Blog-Banner-1-1024x538.jpg\" alt=\"\" class=\"wp-image-1214\" srcset=\"https:\/\/www.srinsoft.engineering\/blogs\/wp-content\/uploads\/2026\/06\/SSE-Blog-Banner-1-1024x538.jpg 1024w, https:\/\/www.srinsoft.engineering\/blogs\/wp-content\/uploads\/2026\/06\/SSE-Blog-Banner-1-300x158.jpg 300w, https:\/\/www.srinsoft.engineering\/blogs\/wp-content\/uploads\/2026\/06\/SSE-Blog-Banner-1-768x403.jpg 768w, https:\/\/www.srinsoft.engineering\/blogs\/wp-content\/uploads\/2026\/06\/SSE-Blog-Banner-1.jpg 1200w\" sizes=\"auto, (max-width: 1024px) 100vw, 1024px\" \/><\/figure>\n\n\n\n<p class=\"wp-block-paragraph\"><strong><em>In piping,&nbsp;it\u2019s&nbsp;all about the flow.<\/em><\/strong>&nbsp;<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">Flow&nbsp;inspires&nbsp;layout,&nbsp;and&nbsp;<a href=\"https:\/\/www.srinsoft.engineering\/design-service\/\" target=\"_blank\" rel=\"noopener\" title=\"\">plant&nbsp;layout&nbsp;design<\/a>&nbsp;starts with understanding the process sequence and operating procedures before anything is placed.&nbsp;&nbsp;<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">In facility layout planning, equipment follows that sequence: pipe rack centered, splitting the unit into distinct areas; pumps in two rows tight on either side of the rack; heat exchangers and vessels grouped in the outer rows.&nbsp;&nbsp;<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">This arrangement minimizes pipe runs and keeps maintenance access&nbsp;honest. Spacing&nbsp;is&nbsp;a layout input. When the logic is right from the start, everything downstream costs less to build and less to run.&nbsp;<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">In this&nbsp;blog&nbsp;article, we cover the most common equipment layout mistakes in piping and plant projects, what they&nbsp;actually cost, and how proper modeling discipline&nbsp;in plant layout design&nbsp;prevents them.&nbsp;<\/p>\n\n\n\n<h2 class=\"wp-block-heading\"><strong>Industrial&nbsp;Design&nbsp;Coordination&nbsp;Issues\u202f\u202f-&nbsp;Plant Layout Mistakes That Delay Commissioning\u202f<\/strong>&nbsp;<\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">Layout mistakes accumulate quietly through early design decisions and surface loudly during detailed engineering, construction, or the first maintenance shutdown.&nbsp;<\/p>\n\n\n\n<h3 class=\"wp-block-heading\">Equipment Placed Without Pipe Routing Logic&nbsp;<\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">Equipment gets positioned first;&nbsp;structural loads, vendor packages, client preferences. Piping is expected to connect the dots later. It always can. The question is at what cost.&nbsp;<\/p>\n\n\n\n<blockquote class=\"wp-block-quote is-layout-flow wp-block-quote-is-layout-flow\">\n<p class=\"wp-block-paragraph\">On a gas compression module, compressors were arranged to balance structural load across the skid. Logical from a civil standpoint. From a piping standpoint, the inlet and discharge nozzles faced the wrong direction for the process sequence, forcing&nbsp;the&nbsp;<a href=\"https:\/\/www.srinsoft.engineering\/design-mechanical\/\" target=\"_blank\" rel=\"noopener\" title=\"\">piping team<\/a>&nbsp;into a layout that added significant pipe length, multiple additional elbows per line, and pressure drops that pushed the design back to process engineering for re-evaluation. The rework happened at 50% detailed design.&nbsp;<\/p>\n<\/blockquote>\n\n\n\n<h3 class=\"wp-block-heading\">Space\u202fUtilization\u202fin&nbsp;Industrial&nbsp;Layout &#8211;&nbsp;Ignoring Maintenance&nbsp;and Access Space&nbsp;<\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">Coordinates in the model are correct. Clearances are not checked. These are not the same&nbsp;thing.&nbsp;<\/p>\n\n\n\n<blockquote class=\"wp-block-quote is-layout-flow wp-block-quote-is-layout-flow\">\n<p class=\"wp-block-paragraph\">On a refinery heat exchanger train, equipment was modeled accurately to P&amp;ID and plot plan.&nbsp;Tube&nbsp;bundle&nbsp;pull lengths were never modeled as live envelopes;&nbsp;they were noted in a datasheet and assumed. When the project reached construction, the pull space for two exchangers was obstructed by structural steel that had already been fabricated. The fix required temporary structural modification during the first planned maintenance window. What was budgeted as a routine turnaround activity became a multi-day civil and rigging operation.&nbsp;<\/p>\n<\/blockquote>\n\n\n\n<figure class=\"wp-block-image size-large\"><img loading=\"lazy\" decoding=\"async\" width=\"1024\" height=\"341\" src=\"https:\/\/www.srinsoft.engineering\/blogs\/wp-content\/uploads\/2026\/06\/Cost-Schedule-impact-reduced-size-1024x341.jpg\" alt=\"\" class=\"wp-image-1219\" srcset=\"https:\/\/www.srinsoft.engineering\/blogs\/wp-content\/uploads\/2026\/06\/Cost-Schedule-impact-reduced-size-1024x341.jpg 1024w, https:\/\/www.srinsoft.engineering\/blogs\/wp-content\/uploads\/2026\/06\/Cost-Schedule-impact-reduced-size-300x100.jpg 300w, https:\/\/www.srinsoft.engineering\/blogs\/wp-content\/uploads\/2026\/06\/Cost-Schedule-impact-reduced-size-768x256.jpg 768w, https:\/\/www.srinsoft.engineering\/blogs\/wp-content\/uploads\/2026\/06\/Cost-Schedule-impact-reduced-size.jpg 1200w\" sizes=\"auto, (max-width: 1024px) 100vw, 1024px\" \/><\/figure>\n\n\n\n<h3 class=\"wp-block-heading\">No Pipe Corridors&nbsp;or Rack Planning<\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">When rack position and routing corridors&nbsp;aren&#8217;t&nbsp;defined early, piping fills available space rather than designated space. So does everything else.&nbsp;<\/p>\n\n\n\n<blockquote class=\"wp-block-quote is-layout-flow wp-block-quote-is-layout-flow\">\n<p class=\"wp-block-paragraph\">On a greenfield petrochemical unit, the pipe rack location shifted twice during early design. Each time, piping routing was updated informally. Instrument cable trays were routed independently by a separate team working from a different model state. When the full model was issued for interdisciplinary&nbsp;<a href=\"https:\/\/www.srinsoft.engineering\/blogs\/bim-clash-detection\/\" target=\"_blank\" rel=\"noopener\" title=\"\">clash detection<\/a>&nbsp;at 60% completion, it flagged over 200 hard clashes \u2014 piping against cable trays, cable trays against str&nbsp;process sequence&nbsp;uctural, piping against access platforms. The resolution took six weeks and pulled four disciplines back into active redesign simultaneously.&nbsp;<\/p>\n<\/blockquote>\n\n\n\n<h3 class=\"wp-block-heading\">Elevation Mistakes&nbsp;<\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">Elevation decisions are&nbsp;actually process&nbsp;decisions with structural and cost consequences attached.<\/p>\n\n\n\n<blockquote class=\"wp-block-quote is-layout-flow wp-block-quote-is-layout-flow\">\n<p class=\"wp-block-paragraph\">On a condensate recovery system, the receiver drum was set at grade based on plot space availability. The assumption was that pumping would handle transfer. What&nbsp;wasn&#8217;t&nbsp;modeled until later was the NPSH requirement for the condensate pumps under actual operating conditions,&nbsp;which required the drum to sit elevated above the pump suction, not at the same level. Two&nbsp;additional&nbsp;pumps and associated pipework were added at&nbsp;detailed&nbsp;design stage. Civil foundations were revised. The correction was entirely avoidable with a 30-minute elevation check at concept layout.&nbsp;<\/p>\n<\/blockquote>\n\n\n\n<h3 class=\"wp-block-heading\">Safety&nbsp;and Clearance Violations&nbsp;<\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">Separation requirements between hazardous equipment are&nbsp;regulatory minimums,&nbsp;and they&nbsp;have to&nbsp;be applied in three dimensions.<\/p>\n\n\n\n<blockquote class=\"wp-block-quote is-layout-flow wp-block-quote-is-layout-flow\">\n<p class=\"wp-block-paragraph\">On a chemical processing unit, a fired heater was positioned within restricted separation distance of a flammable liquid pump, based on a plot plan review that&nbsp;didn&#8217;t&nbsp;account for the actual equipment footprints and radiation zones in 3D. The layout passed&nbsp;internal&nbsp;review. It failed third-party HAZOP at 70% model completion.&nbsp;The area required&nbsp;a full&nbsp;redesign;&nbsp;equipment relocated, pipe rack rerouted, structural supports repositioned.&nbsp;The schedule&nbsp;impact ran&nbsp;to&nbsp;several weeks. The entire situation traces back to a clearance check that should have been run at layout&nbsp;freeze.&nbsp;<\/p>\n<\/blockquote>\n\n\n\n<h3 class=\"wp-block-heading\">Expansion&nbsp;Not&nbsp;Considered&nbsp;<\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">A plant that has no room to grow transfers that&nbsp;constraint to&nbsp;the client permanently.<\/p>\n\n\n\n<blockquote class=\"wp-block-quote is-layout-flow wp-block-quote-is-layout-flow\">\n<p class=\"wp-block-paragraph\">A utility block was designed tight to the battery limit to maximize plot efficiency. Eighteen months after commissioning, the client requested a capacity expansion that&nbsp;required&nbsp;one&nbsp;additional&nbsp;boiler and associated pipework. There was no room without&nbsp;relocating&nbsp;active infrastructure. Temporary bypasses, live system tie-ins, and partial demolition of recently commissioned work turned a straightforward capacity addition into a project&nbsp;nearly as&nbsp;complex as the original build.&nbsp;<\/p>\n<\/blockquote>\n\n\n\n<h2 class=\"wp-block-heading\"><strong>Factory Layout Design &#8211;&nbsp;The Hidden Cost&nbsp;of Layout Mistakes<\/strong>&nbsp;<\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">Layout errors that surface at concept stage cost time in a meeting room. The same errors found at detailed design pull civil, structural, piping, and instruments back into active work simultaneously. By that point, foundations may be designed, steelwork may be fabricated, and procurement may be in progress. A single equipment shift moves everything connected to it.&nbsp;<\/p>\n\n\n\n<figure class=\"wp-block-image size-large\"><img loading=\"lazy\" decoding=\"async\" width=\"1024\" height=\"341\" src=\"https:\/\/www.srinsoft.engineering\/blogs\/wp-content\/uploads\/2026\/06\/Inner-Banner-1-1-1024x341.jpg\" alt=\"\" class=\"wp-image-1217\" srcset=\"https:\/\/www.srinsoft.engineering\/blogs\/wp-content\/uploads\/2026\/06\/Inner-Banner-1-1-1024x341.jpg 1024w, https:\/\/www.srinsoft.engineering\/blogs\/wp-content\/uploads\/2026\/06\/Inner-Banner-1-1-300x100.jpg 300w, https:\/\/www.srinsoft.engineering\/blogs\/wp-content\/uploads\/2026\/06\/Inner-Banner-1-1-768x256.jpg 768w, https:\/\/www.srinsoft.engineering\/blogs\/wp-content\/uploads\/2026\/06\/Inner-Banner-1-1.jpg 1200w\" sizes=\"auto, (max-width: 1024px) 100vw, 1024px\" \/><\/figure>\n\n\n\n<h3 class=\"wp-block-heading\">Cost<\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">Rework&nbsp;cost&nbsp;is&nbsp;exponential. A layout correction at 60% detailed design triggers revised drawings across multiple disciplines, potential re-procurement, and contractor variation claims if construction has started.&nbsp;Everything around the equipment&nbsp;got&nbsp;more expensive to move.<\/p>\n\n\n\n<h3 class=\"wp-block-heading\">Schedule&nbsp;<\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">Every interdisciplinary ripple adds&nbsp;non-recoverable time. One nozzle orientation&nbsp;change&nbsp;updates the piping isometric, which affects the support steel location, which touches the civil foundation drawing. Each discipline has its own review and reissue cycle. Schedule slips in layout-driven rework&nbsp;multiply, because&nbsp;the disciplines&nbsp;aren&#8217;t&nbsp;waiting in sequence.&nbsp;They&#8217;re&nbsp;all affected at once.&nbsp;<\/p>\n\n\n\n<h3 class=\"wp-block-heading\">Operability&nbsp;<\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">This is the cost that never appears in a project close-out report. A plant that is difficult to&nbsp;operate, inspect, or&nbsp;maintain&nbsp;transfers that burden to the client for the life of the asset. Maintenance windows run over.&nbsp;Access&nbsp;workarounds become standard practice. Unplanned shutdowns happen more&nbsp;frequently&nbsp;than they should. The layout decision that caused it was made years earlier, under schedule pressure, by a team that never saw the consequence.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\"><strong>3D Factory Layout Design &#8211;&nbsp;How Proper Modeling Helps<\/strong><\/h2>\n\n\n\n<h3 class=\"wp-block-heading\">Layout Logic Before Model Population<\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">For layout,&nbsp;the model needs to carry layout logic from the start \u2014 process sequence driving equipment arrangement, rack position defined before piping begins, routing corridors&nbsp;established&nbsp;as constraints. When the model is built around layout rules, the clash count at 60% drops substantially&nbsp;and&nbsp;the clashes that&nbsp;remain&nbsp;are genuine coordination issues.&nbsp;<\/p>\n\n\n\n<h3 class=\"wp-block-heading\">Maintenance Envelopes&nbsp;and Safety Zones&nbsp;as Modeled Objects<\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">Modeling maintenance envelopes and safety exclusion zones as actual geometry in the&nbsp;<a href=\"https:\/\/www.srinsoft.engineering\/other-bim-service\/\" target=\"_blank\" rel=\"noopener\" title=\"\">3D environment<\/a>&nbsp;means they&nbsp;participate&nbsp;in clash detection, show up in model reviews, and create a visible constraint that&nbsp;has to&nbsp;be resolved. What gets modeled gets checked.&nbsp;&nbsp;<\/p>\n\n\n\n<h3 class=\"wp-block-heading\">Interdisciplinary Coordination Inside&nbsp;the Model<\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">Layout errors compound when disciplines work in separate environments. Piping routes to one model state, structures respond to&nbsp;another,&nbsp;instruments work from a P&amp;ID that&nbsp;hasn&#8217;t&nbsp;caught up with either. A single federated model with layout freeze enforced as an actual milestone stops that cascade before it starts.<\/p>\n\n\n\n<h3 class=\"wp-block-heading\">Early Review&nbsp;at&nbsp;the Right Stage<\/h3>\n\n\n\n<p class=\"wp-block-paragraph\">A targeted layout audit at&nbsp;30% \u2014&nbsp;equipment arrangement against&nbsp;<a href=\"https:\/\/www.srinsoft.engineering\/blogs\/piping-engineering-and-design-guide\/\" target=\"_blank\" rel=\"noopener\" title=\"\">process sequence<\/a>, rack position against routing corridors, maintenance access against spacing \u2014 catches the mistakes that cost most to fix later. Not a full clash review. One structured review at the right stage eliminates weeks of reactive rework downstream.&nbsp;<\/p>\n\n\n\n<h2 class=\"wp-block-heading\"><strong>Layout&nbsp;is Not a Phase<\/strong><\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">Good layout thinking is simple: place equipment so that piping runs short, straight, accessible, and safe.&nbsp;&nbsp;<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">But each discipline has its own priorities and its own timeline. Piping wants short runs. Civil&nbsp;wants&nbsp;stable foundations. Structural wants&nbsp;load&nbsp;balance. Instruments want cable access. When schedule pressure hits, each discipline solves its own problem \u2014 and the layout logic that was agreed at the start quietly gets compromised.&nbsp;<\/p>\n\n\n\n<p class=\"wp-block-paragraph\">The teams that do it well&nbsp;don&#8217;t&nbsp;treat layout as a phase. They treat it as a constraint that never switches off.&nbsp;<\/p>\n\n\n\n<h2 class=\"wp-block-heading\"><strong>Work With a Team That Catches It Early<\/strong><\/h2>\n\n\n\n<p class=\"wp-block-paragraph\">If your projects are carrying layout risk into&nbsp;detailed&nbsp;design,&nbsp;it&#8217;s&nbsp;worth a conversation.&nbsp;<a href=\"http:\/\/192.168.3.90\/srinsoftengg\/\" target=\"_blank\" rel=\"noreferrer noopener\">Srinsoft&nbsp;Engineering<\/a>&nbsp;works with plant and piping teams to bring layout discipline into the model from day one,&nbsp;before the cost of fixing it compounds.&nbsp;<\/p>\n\n\n\n<h3 class=\"wp-block-heading\">FAQs&nbsp;<\/h3>\n\n\n\n<div data-schema-only=\"false\" class=\"wp-block-aioseo-faq\"><h3 class=\"aioseo-faq-block-question\">1.\u00a0<strong>Why do we still get clashes even after doing\u00a0proper\u00a0layout?<\/strong>\u00a0<\/h3><div class=\"aioseo-faq-block-answer\">\n<p class=\"wp-block-paragraph\">Because what you call&nbsp;\u201cproper&nbsp;layout\u201d is often just equipment placement, not&nbsp;flow-driven layout. If pipe routing logic, access zones, and rack positions&nbsp;weren\u2019t&nbsp;locked early, clashes are inevitable.&nbsp;&nbsp;<\/p>\n<\/div><\/div>\n\n\n\n<div data-schema-only=\"false\" class=\"wp-block-aioseo-faq\"><h3 class=\"aioseo-faq-block-question\">2.\u00a0<strong>When should layout\u00a0actually be\u00a0frozen in a plant model?<\/strong>\u00a0<\/h3><div class=\"aioseo-faq-block-answer\">\n<p class=\"wp-block-paragraph\">Around&nbsp;<strong>30% design<\/strong>. If layout is still moving at 50\u201360%,&nbsp;you\u2019re&nbsp;already in rework territory. At that point, piping, structure, and procurement are reacting to changes instead of building forward.<\/p>\n<\/div><\/div>\n\n\n\n<div data-schema-only=\"false\" class=\"wp-block-aioseo-faq\"><h3 class=\"aioseo-faq-block-question\"><strong>3. Why does a small equipment shift cause so much delay?<\/strong><\/h3><div class=\"aioseo-faq-block-answer\">\n<p class=\"wp-block-paragraph\">Because nothing is isolated.&nbsp;You\u2019re&nbsp;not moving equipment.&nbsp;You\u2019re&nbsp;triggering a&nbsp;<strong>multi-discipline chain reaction<\/strong>, which is why late changes&nbsp;explode&nbsp;cost and schedule.&nbsp;<\/p>\n<\/div><\/div>\n\n\n\n<div data-schema-only=\"false\" class=\"wp-block-aioseo-faq\"><h3 class=\"aioseo-faq-block-question\"><strong>4.\u00a0<strong>Why is pipe length increasing compared to\u00a0initial\u00a0estimates?<\/strong>\u00a0<\/strong><\/h3><div class=\"aioseo-faq-block-answer\">\n<p class=\"wp-block-paragraph\">Because&nbsp;layout&nbsp;wasn\u2019t&nbsp;driven by process flow. Equipment got placed for \u201cfit\u201d or structural convenience, and piping had to compensate. Longer routes, more bends, more cost.&nbsp;That\u2019s&nbsp;a layout failure, not a piping issue.&nbsp;<\/p>\n<\/div><\/div>\n\n\n\n<div data-schema-only=\"false\" class=\"wp-block-aioseo-faq\"><h3 class=\"aioseo-faq-block-question\"><strong><strong>5. Why did this pass model\u00a0review but\u00a0fail during construction or HAZOP?<\/strong><\/strong><\/h3><div class=\"aioseo-faq-block-answer\">\n<p class=\"wp-block-paragraph\">Because reviews checked&nbsp;<strong>geometry<\/strong>, not&nbsp;<strong>real constraints<\/strong>.&nbsp;Clearances, safety distances, radiation zones, maintenance access. If these&nbsp;weren\u2019t&nbsp;modeled and verified in 3D, the \u201capproved\u201d layout was never actually buildable or compliant.&nbsp;<\/p>\n<\/div><\/div>\n","protected":false},"excerpt":{"rendered":"<p>In piping,&nbsp;it\u2019s&nbsp;all about the flow.&nbsp; Flow&nbsp;inspires&nbsp;layout,&nbsp;and&nbsp;plant&nbsp;layout&nbsp;design&nbsp;starts with understanding the process sequence and operating procedures before anything is placed.&nbsp;&nbsp; In facility [&hellip;]<\/p>\n","protected":false},"author":13,"featured_media":1214,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"om_disable_all_campaigns":false,"_monsterinsights_skip_tracking":false,"_monsterinsights_sitenote_active":false,"_monsterinsights_sitenote_note":"","_monsterinsights_sitenote_category":0,"site-sidebar-layout":"default","site-content-layout":"","ast-site-content-layout":"","site-content-style":"default","site-sidebar-style":"default","ast-global-header-display":"","ast-banner-title-visibility":"","ast-main-header-display":"","ast-hfb-above-header-display":"","ast-hfb-below-header-display":"","ast-hfb-mobile-header-display":"","site-post-title":"","ast-breadcrumbs-content":"","ast-featured-img":"","footer-sml-layout":"","theme-transparent-header-meta":"","adv-header-id-meta":"","stick-header-meta":"","header-above-stick-meta":"","header-main-stick-meta":"","header-below-stick-meta":"","astra-migrate-meta-layouts":"default","ast-page-background-enabled":"default","ast-page-background-meta":{"desktop":{"background-color":"var(--ast-global-color-4)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"tablet":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"mobile":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""}},"ast-content-background-meta":{"desktop":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"tablet":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"mobile":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""}},"footnotes":""},"categories":[5],"tags":[],"class_list":["post-1213","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-design"],"aioseo_notices":[],"_links":{"self":[{"href":"https:\/\/www.srinsoft.engineering\/blogs\/wp-json\/wp\/v2\/posts\/1213","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.srinsoft.engineering\/blogs\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.srinsoft.engineering\/blogs\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.srinsoft.engineering\/blogs\/wp-json\/wp\/v2\/users\/13"}],"replies":[{"embeddable":true,"href":"https:\/\/www.srinsoft.engineering\/blogs\/wp-json\/wp\/v2\/comments?post=1213"}],"version-history":[{"count":3,"href":"https:\/\/www.srinsoft.engineering\/blogs\/wp-json\/wp\/v2\/posts\/1213\/revisions"}],"predecessor-version":[{"id":1220,"href":"https:\/\/www.srinsoft.engineering\/blogs\/wp-json\/wp\/v2\/posts\/1213\/revisions\/1220"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.srinsoft.engineering\/blogs\/wp-json\/wp\/v2\/media\/1214"}],"wp:attachment":[{"href":"https:\/\/www.srinsoft.engineering\/blogs\/wp-json\/wp\/v2\/media?parent=1213"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.srinsoft.engineering\/blogs\/wp-json\/wp\/v2\/categories?post=1213"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.srinsoft.engineering\/blogs\/wp-json\/wp\/v2\/tags?post=1213"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}